Ground is broken for the planned production area
expansion
On account of the continuing high demand we have decided to
expand our production facilities. The useful floor space will be
enlarged from 15,000 m² to 17.000 m², with a
supported height of 14 m!
Our company is going to install the following for you in the
new production hall:
- an annealing furnace measuring 20,5 x
7,5 x 5 m
- a sandblasting cabin and
- a painting line measuring 18 x 7,5
x 6 m
in line with the very latest quality and environmental aspects
The new production facilities are to be ready at the end
of March 2007. The whole building will be set up as a
pre-fabricated component structure made of reinforced concrete,
taking the latest heat insulation aspects into
account
In both parts of the new hall building, two each gantry cranes
systems which can be used over the complete length of the hall
areas will be ready for use, with a hook height of
9 m.